SIPs WEEK Event Delayed Until Oct 28th - 31st

Well, we have had our first official delay in construction. Two things happened at the same time that actually worked out in the end. One, it is taking us a bit longer to get our plumbing permits and second bank draw than anticipated. This is causing us to not be able to finish the slab […]

“A Clean Break” Prefab Neighborhood Opens Tonight at 7PM

I don’t know how I forgot to post anything on this event until now. Get ready for lots of links in this post. A Clean Break sponsored and coordinated by Minima is part of the Design Philadelphia citywide event that is starting today and running for a week straight with over 90 programs scheduled.

ISA was […]

Time to Start Finalizing Finishes - To Do List

Now that construction is moving along and our target end date can be measured in weeks, it’s time to get down to the details. There are a lot of items on the to do list as far as finalizing materials, finishes and design. This post is as much an aide to the team as it […]

Foundations Completed on the 100K House Project

The end of week two of construction marks the completion of the foundation. Tino surprised us and came out on Saturday evening after to wrap up the foundation work. In a matter of hours, he and one helper installed insulation, backfilled the entire site and leveled the interior of the foundations in preparation for slab […]

Construction Update - Week 2 (Video and Photo Recap)

Week two of construction has come to a close and we already have the footers and foundation walls finished. Next week will be prep and pouring of the slabs. Check out the video and image recaps below.
100K House Construction Video - Week 2

Week 2 Construction Photos
In week two we went from poured footers to formed […]

SIPs WEEK Event - Oct 21st - 24th - Sponsored by SURETIGHT

Construction is moving right along and we’re less than two short weeks away from having our SIPs (Structurally Insulated Panels) delivered by SURETIGHT. From the outset of our SIPs investigation and quoting, we were looking for a company that would not only deliver a great product, but one that was also on board with our […]

Foundation Wall Forms in Place and Ready to Pour Concrete

Well the foundation wall forms are almost completely in place. As I type, Tino’s crew is at the site buttoning up the last sections. Hopefully the rain will hold off so we can pour them today also. Below are a couple of photos we snapped at the end of the day.

You can see in the […]

Construction Images of the 100K House Project

We are trying to do a couple of things each week to keep everyone up to date on the construction process of the 100K House project. Nic will be taking video throughout each week and compiling it into a weekly recap. I have weekly LEED and Budget recaps on my list to do as well. […]

Alternate Ideas for Stairway Wall?

I love the look of the white stairway wall designed by ISA. It is clean, simple and modern without using expensive materials. At the same time, I struggle at times with the concept. I think the main thing is that I worry it will block too much of the light coming in from the windows […]